This is a step by step Two Day Roof Installation on Curtis Total Service Inc.
Corporate Headquarters located at 1415 Pennsylvania Street, Allentown, PA
Curtis Total Service Inc. Specializes in drain cleaning, excavation, hydro-jetting, sewer line location, maintenance products,septic systems,
 video pipe inspection, gas furnaces, thermostats, heat pumps, air conditioning, air filtration, humidifiers, water sanitizers, e-gress windows, filtration systems, water softeners, bathroom, kitchen & basement remodeling,drainage solutions, sun rooms, additions, and much more.
Call or click below for prompt, professional service. 
 24 Hour  Emergency Service (610) 770-9045  
 

Monday - Day One

 

8:00 A.M. Step # 1  Hang Tarps Over Gutters On Edge Of Roof.  

(Protect Building And Landscaping)

 

9:00 A.M. Step # 2 Remove Existing Roof Shingles.

 

 

12:00 P.M. Step # 3 Clean Roof Deck And Make Wood Repairs.

 

 

2:00 P.M. Step #4  Install Aluminum Roof Edge.

 

 

2:30 P.M. Step #5   Install    Along Roof Edge.

 

 

3:00 P. M. Step #6  Install  Over Entire Roof Deck.

 

 

3:30 P. M. Step #7  Install   Along Wall Under

Step Flashing. (GAF-ELK Installation Recommendation).

 

 

 

5:00 P.M. Step # 8 Clean Entire Property.

 

Madden Enterprises Roofing Divison 

GAF-ELK License# CE16410

 

The Following Components Are Required For The 

Weather Stopper System Plus Warrenty 

 

 

Tuesday -Day Two
 
8:00 A.M. Step #1 Bradco Supply Arrives On Site.
 
 
8:30 A.M. Step # 2  Load Roofing Materials On Roof Deck. 
 
 
9:00 A.M. Step # 3 Begin The Installation Process.
 
 
9:15 A.M. Step #4  Install   Starter Strip.
 
 
10:00 A.M. Step # 5  Install Step Flashing.
 
 
9:00 A.M.-3:00 P.M Step#6 Install  (Hickory).
Install Shingles With Six Nails (GAF-ELK Installation Recommendation).
 
 
3:00 P.M. Step # 7  Install Three    Power Ventilation Units.
.
 
3:15 P.M. Step # 8 Install Ridge Vent.
 
 
3:45 P.M. Step #9 Install  Ridge Cap Shingles.
 
 
5:00 P.M. Installation Complete.